|
Efficiency
Recommendations
All equipment
must meet DOE and local building code standards, which usually
reference ASHRAE 90.1. By law, DOE is required to maintain
the federal minimum-efficiency standards at levels at least
as stringent as the most recent revision of ASHRAE 90.1. ACEEE
recommends buying more efficient equipment instead of baseline
units. In general, the premium price of more efficient equipment
is recovered quickly for commercial unitary equipment because
it is generally used many more hours per year than residential
equipment in the same climate zone. The recommended minimum
level from the New Buildings Institute is also the Consortium
for Energy Efficiency Tier 2 level.

Consortium
for Energy Efficiency Tier 2 recommendations, corresponding
to ENERGY STAR for units larger than 65,000 Btuh, point toward
very efficient packaged air conditioners and heat pumps. Federal
Energy Management Program materials are also excellent;
the site includes cost-effectiveness calculation methods.
ENERGY STAR and CEE both set 85% AFUE as their recommendation
for efficient "small" boilers. In cold climates,
condensing boilers may be very cost-effective (AFUE at least
90%).
Sizing
There
are enough unique situations in selecting the proper packaged
air conditioning unit that a heating and cooling load calculation
should always be done. Using rules of thumb for sizing is
inaccurate and not recommended. Correctly sizing the cooling
capacity of a unit must take into consideration the envelope
load (orientation, windows, walls, and roof), the internal
heat gains (lights, people, and equipment), and the ventilation
load. Ask the designer to submit calculations for your records.
At least you will know if she/he did them. ASHRAE and other
sources have proven methods for calculating heating and cooling
loads.
Once the calculations are complete, the unit should be sized
to barely meet the maximum demand under the ASHRAE design
temperature for the location. Oversized units consume more
energy than units sized for the expected load. Furthermore,
oversized units cause space temperature fluctuations as the
compressors "short-cycle" in an attempt to meet
part-load conditions. A common refrain from designers is that
they oversize equipment so that it will have capacity to warm
up or cool down the space quickly after a prolonged night
setback. However, during the unoccupied warm-up cycle the
ventilation air is off and any capacity in the equipment for
ventilation serves as a cushion.
Layout
and Installation
Lifecycle
efficiency depends on access and clearance for service and
maintenance. Units that are not serviced regularly become
energy "hogs." When equipment is crammed into a
ceiling or attic space, and a service technician has to stand
on a ladder in a busy office to service the unit, chances
are the unit will not be serviced regularly. When planning
for proper maintenance access, take into consideration that
filters must be changed (sometimes quarterly); electrical
panels must be accessible; and compressors, fans, belts, shafts,
bearings, and coils must occasionally be replaced.
Adequate
clearance must be afforded to the intake and exhaust of the
air-cooled equipment. Locating an air-cooled unit too close
to a wall or in a pit can restrict the proper airflow or cause
recirculation of the heat rejected from the fan. Putting multiple
condensers near each other in a "pen" or enclosure
can lead to cross-feeding hot exhaust air from one to the
cooling fins of adjacent units under some conditions. Split-system
air conditioners and heat pumps require careful design of
refrigerant piping. Returning lubricating oil from the piping
and coils to the compressor is a major concern. Outdoor units
should be located as close to Indoor units as possible. There
are restrictions on how high above and how far below the outdoor
unit can be relative to the indoor unit. Improper refrigerant
piping design can waste energy and operating dollars.
In selecting
outdoor packaged equipment for either humid locations or very
cold climates, special attention needs to be paid to cabinet
insulation and sealing. Additional insulation may be needed
to prevent condensation from forming on the outsides of casings,
and doors may need to be tightly sealed to prevent leakage.
Since packaged units are manufactured on an assembly line,
careful inspection must be given at the time of installation
to assure that these issues are addressed.
Completion
(Commissioning) Requirements
Of prime
importance to successful long-term energy efficiency are the
steps taken at the time of project completion to assure that
the packaged equipment and systems are working properly and
that an orderly transition occurs from the contractor to the
owner. Activities include:
- Startup
and testing of all equipment
- Owner
training on operation
Reports
documenting these activities include:
- Testing,
adjustment, and balancing (TAB) reports
- Drawings
of the as-built installation
- Narrative
descriptions of all systems (may not be required on through-the-wall
and single-zone systems)
- Complete
operation and maintenance manuals including:
- locations
of qualified service agencies
- data
on each piece of equipment (i.e., capacities, options,
etc.)
- operating
instructions for each piece of equipment
- preventative
maintenance measures
- electrical
wiring diagrams
- spare
parts list
- control
sequences
Service
and Maintenance
Some
owners of larger buildings (or multiple buildings) employ
full-time maintenance staff, but owners of smaller buildings
usually make other arrangements. If you do not have full-time
staff available for maintenance, it is wise to retain a qualified
maintenance service organization. Some owners choose to wait
until the equipment fails before calling a service company,
but this may cost more in the long run in repairs and higher
bills. Even smaller buildings with packaged equipment may
be complicated enough to require the services of a qualified
service company.
Your
maintenance program should at minimum include the following:
- Regular
air filter changes (this may be required on a quarterly
basis)
- Annual
verification of the operation of critical elements such
as fan belts, compressors, and dampers
- Cleaning
cooling coils, condenser coils, fans, and condensate drains
- Verification
and calibration of controls
- Checking
refrigerant levels-too low or too high impacts energy performance
- Checking
gas-burning equipment
|